Page 24 - Hitachi IR 2025
P. 24
CASE STUDIES
Addressing Delhi's
growing power demand
during summer
A case study
The Company
commissioned the Gas
Insulated Switchgear
(GIS) Power Transformer
Bay extension for Tata
Power Delhi Distribution
Limited (TPDDL) ahead
of the scheduled time,
strengthening the
grid and showcasing
its efficiency to serve
Delhi’s growing
power demand in the
summer season.
Hitachi Energy India
Limited has completed and
commissioned the GIS Bay
extension and associated
works with supply and
installation at 66/11 kV
Karala, Delhi for TPDDL.
As against the contractual
completion due date of
August 2025, the project, was
expedited given the growing
power demand in Delhi’s
summer season. Considering
this, the customer’s early
requirement for power
was acknowledged by the
Company from April 2025.
The project was successfully
commissioned on March 31,
22 Hitachi Energy India Limited